LOCATION

COLONGRA, CENTRAL COAST , NEW SOUTH WALES

CLIENT

LIBERTY INDUSTRIAL / DELTA ELECTRICITY

JOB DESCRIPTION

Two Chimney Stacks Removal of 20 bonded ACM vent pipes from a height of 154m. DBC provided the access consultancy and engineered Husik mobile circumferential temporary platform access system. Climb ascent to establish anchors using IRATA rope access alpine techniques and to enable powered access to the top of both chimneys in order to lift technicians and equipment. Installed rigging and circumferential platforms, then established water and air services to the top and completed the core-drilling through 230mm thick shell to remove ACM vents, lower to ground and sampled surrounds for ACM clearance certificate.

SERVICES PROVIDED

ACCESS CONSULTANCY / ENGINEERED HUSIK TEMPORARY ACCESS SYSTEM FOR RIGGING, ANCHORAGE AND MOBILE PLATFORM / ESTABLISH ROPE ACCESS TO TOP OF 2 X 154 METRE CHIMNEY STACKS / CORE-DRILLING / ASBESTOS REMOVAL

TESTIMONIAL

Two large chimneys could not be demolished before the vents were safely removed. The project required exceptional expertise at height. DBC technicians are rope access professionals and they provide access in a rare combination with refractory experience. The challenge of the particular scope was considerable and DBC were chosen due to their excellent safety record and their ability to meet our HSEQ compliance requirements. DBC's documentation is of a very high standard.

LIBERTY INDUSTRIAL, DIRECTOR, HSEQ MANAGER

CONTACT US

CONNECT
WITH
US

CONTACT US

CONNECT WITH US